Barrow Mill

Sector:
Commercial and Residental

Location:
Barrow-in-Furness, Cumbria

Client:
Eric Wright Civil Engineering Ltd

Date:
2020

Within the TM5 building, we constructed a new 50m x 15m reinforced concrete machine floor to support paper processing equipment. The basement works included floor slabs with drainage channels, pile caps, columns, and a water catch pit. The upper floor featured two 50m-long spine beams with suspended slabs laid to crossfalls. Delivered during Covid restrictions and within an existing structure, the project reflected our technical capability under challenging conditions.

Project Images

Let’s Build Together

Have a question about our reinforced concrete service? Drop us a message.

Contact Us
Contact Us